  • April 2018

    • Pavement removals and the closure of the Blake Road Bridge between Hiawatha Avenue and Oxford Road

  • May 2018

    • Underground utility work and short closure at Blake Road around train tracks

  • June 2018

    • Intersection of Blake Road and Excelsior Boulevard closed for a weekend

  • July 2018

    • Paving and utility line replacement

  • August 2018

    • Blake Road Bridge reopens

  • April 2019

    • Construction commences for 2019 construction season

  • Summer 2019

    • Project completion

*This timeline will be updated as more information becomes available.